Minnetonka council approves three sidewalk and road contracts totaling about $3.23 million
Summary
The council awarded construction contracts for Red Circle Drive ($299,857.40), Shady Oak Road ($199,977) and Cedar Lake Road & Ridgedale Drive ($2,731,859.51), authorizing the city engineer to expend funds up to each project's budget caps (various TIF and budget sources). Construction slated for spring and summer.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
City project manager Mr. Manchester presented three competitive-bid recommendations and the council approved all three contract awards in a single meeting.
He recommended awarding Project 23607 (Red Circle Drive sidewalk improvements) to Clark Companies for $299,857.40 and authorized the city engineer to expend funds without further council approval provided total project cost does not exceed a $600,000 budget. The project includes an 8-foot sidewalk, storm sewer and road improvements and easement-related sign relocation.
Project 26607 (Shady Oak Road sidewalk improvements) was also recommended to Clark Companies for $199,977, with a project budget cap of $425,000; work includes sidewalk widening, a 4-foot boulevard, storm improvements and pedestrian-signal modifications coordinated with Hennepin County.
Project 26609 (Cedar Lake Road and Ridgedale Drive improvements) was presented with a low bid from Park Construction Company of $2,731,859.51 and a project budget cap of $4,700,000. That project includes a 2-inch mill and overlay in multiple sections, signal replacements, curb and sidewalk repairs, striping, shoulder and bike-lane additions, and other improvements timed to minimize disruption to school operations.
Council approved the awards by roll call. Staff noted projects are funded through TIF and budget allocations; construction start dates were described as spring/summer with communications and email updates to affected residents.
Why it matters: the contracts fund pedestrian and safety upgrades and road resurfacing planned to improve connectivity, traffic calming and pedestrian access in several parts of Minnetonka; the council authorized the city engineer to manage within the stated project budgets.