Glendale says downtown campus project is nearing building completion; move‑in eyed for mid‑May
Summary
City staff told the City Council the Downtown Campus Reinvestment Project is on track, with the building portion close to substantial completion and site work and Murphy Park hardscape continuing into mid‑May; move‑in is targeted for mid‑May with a ribbon cutting planned for mid‑June.
Miss Barber, presenting Update No. 41 for the Downtown Campus Reinvestment Project, told the Glendale City Council on March 24 that construction is progressing and that the building portion is "within about a little over a month from substantial completion." She said recent photos show the plaza concrete poured and that trees, irrigation and other site hardscape work are being installed around the new city hall campus.
The presentation described progress across several project areas: sidewalks and reinforcement bars are in place along Glendale Avenue and Glen Drive; the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat