County staff and consultants presented comprehensive Title 10 updates and design‑guideline revisions to align airport minimum standards with modernization projects. The board approved Title 10 and the design guidelines in first readings and affirmed the airport modernization plan for location and extent review.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Pitkin County’s Board of County Commissioners reviewed a multi‑part package of ordinance and resolution actions March 11 as part of the Aspen/Pitkin Airport modernization effort.
Airport Director Diane Jackson and consultants described a 20‑year overdue update to Title 10 (the county’s airport minimum standards) that incorporates changes in FAA policies, lease requirements and emerging technologies such as aircraft self‑fuelling and electrification. Dan Bartholomew and the airport team said the update codifies current lease practices, clarifies security and operational standards and gives staff regulatory tools to ensure uniform treatment of airport users.
The board also considered updated Airport Design Guidelines. Staff said the 2014 guidelines needed revision to reflect the Common Ground recommendations, the airport advisory board’s input and recent master‑planning work; the revised guidelines will guide architecture, site improvements and construction management during the modernization.
On the airfield side, project managers showed a conceptual 15–30% design set that includes an 80‑foot west shift of the runway, a roughly 9–10 foot runway elevation change, new approach lighting and a proposed airfield lighting vault. Staff outlined 2026 enabling projects — staging and laydown areas, temporary accesses to reduce truck traffic on Highway 82, potential on‑site asphalt batching and significant utility relocations — and stressed the need to coordinate timing with Holy Cross Energy, water providers and CDOT.
Commissioners held questions on utilities and the risks of subsurface water at the airport; staff described a multi‑pronged drainage approach (piping Al Creek further into the hillside, under‑drains and targeted reconstructive grading) and said construction sequencing and early contractor involvement will reduce the risk of unexpected delays.
The board approved changes to Title 10 and the design‑guideline resolution and affirmed the modernization materials for location & extent review; staff will continue detailed design and permitting and return to BOCC for subsequent approvals as projects near construction readiness.
Speakers quoted in this article spoke at the Pitkin County BOCC meeting on March 11, 2026. Project materials and FAA coordination documents are the technical sources for design concepts described here.