Committee advances Golden Hill traffic-signal projects, staff warns federal grant is uncertain
Summary
Ulster County’s public works committee approved a series of resolutions to fund a traffic signal and related infrastructure at Route 32 and Golden Hill Lane, including contracts and developer cost-sharing; staff warned the federal congressionally directed funds that would cover part of the work are slow and may not materialize.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Ulster County’s Public Works and Capital Projects Committee on Feb. 10 voted to advance multiple measures to install a traffic signal at Route 32 and Golden Hill Lane and to fund related infrastructure improvements.
The committee moved Resolution No. 19 to amend the county’s 2025–2030 capital improvement program for the Golden Hill Transportation Improvements and later approved related contracts and developer cost-sharing resolutions. The committee approved a contract with Jor Excavating Inc. and a $300,000 developer contribution agreement with Golden Hill Owner LLC; members recorded an abstention on at least one vote for employment-related conflict concerns.
Why it matters: The project ties local capital actions to a congressionally directed federal grant that county staff said is not yet secure, creating uncertainty about who ultimately pays for components of the work.
County planning staff member Mr. Doran told the committee that “this funding literally is coming from a congressionally directed uh funding initiative,” and explained that the county is structured to act as a pass-through subrecipient to the developer pending receipt of the federal money. He warned the funding process with HUD is “abysmally slow and it may disappear,” and said the deal as drafted would withhold any county payments until federal funds arrive.
Doran also flagged an implementation complication tied to domestic-purchase rules: he said the federal grant includes a Buy America-type provision that could expose parts of the low- and moderate-income housing project to additional requirements if developer funds were used directly; to avoid that exposure, the county and developer agreed to a pass-through arrangement and an eventual 50/50 split of eligible costs if the grant is received.
Committee members asked technical and contracting questions about inspection contracts and contingency amounts; staff noted a separate construction inspection contract under $50,000 that would not require full legislative approval. Where votes were recorded, the committee advanced the measures out of committee for floor consideration (committee vote counts were reported in the meeting for the record).
Next steps: Resolutions approved by the committee proceed to the full Legislature for final action; staff said no county payments will be made to the developer until federal grant funds have been received and accounted for.