Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Board highlights capital work: security vestibules, MHS atrium renovation and a $175,000 Hillrest roof change order

Morris School District Board of Education · July 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent and finance staff summarized ongoing building projects including security vestibules, MHS atrium renovations, roofing and lab updates; the board was told of an unexpected $175,000 change order for the Hillrest roof but that the project remained within a $250,000 change-order allowance.

Superintendent Dr. Mucci and finance leaders told the Morris School District Board of Education about an active summer of facilities work — from security vestibules and an MHS atrium renovation to new science labs — and reported an unexpected $175,000 change order on the Hillrest roof project that remains within the project’s change-order allowance.

Dr. Mucci opened the facilities update by listing district-wide activity: security vestibules at Woodland, FMS and MHS, the MHS atrium and guidance-suite renovation, and roofing, paving and painting projects across multiple sites. “The district is bustling with a tremendous amount of activity at all sites as we make significant building plan improvements,” she said.

Finance committee speaker Linda provided further detail on sites and work: HVAC duct work and stage work in the auditorium, replacement of gym and pool roofs, guidance-area renovations and plans to update six science labs using primarily internal resources. On change orders, she said the Hillrest roof contractor submitted a $175,000 change order described as “terribly high and really unexpected,” but noted the amount falls under a $250,000 allowance for change orders on that project.

Energy and financing pilot: Linda also described a pilot LED lighting upgrade using JCP&L utility incentives with contractor Priority One Heating and Cooling. Using the example the board was given, a $100,000 lighting project could receive a 45% utility incentive; the district would finance remaining costs through a zero-interest, five-year lease-purchase agreement to capture operating-cost savings and roll out additional projects over a 3–5 year period.

Personnel and donations: The meeting included formal introductions of new building principals — Colleen Myers at Thomas Jefferson School and Mr. Fallon at another elementary site — both of whom spoke about beginning in mid-August and engaging families. The board also acknowledged donations including an alto saxophone from alumnus Stuart Heiser and monetary gifts for library books and school programs.

What this means: The Hillrest roof change order will affect project accounting and was flagged for attention even though finance staff said it did not exceed the project’s contractual change-order allowance. The lighting pilot offers a financing model the district hopes to extend to other infrastructure upgrades.

Next steps: Staff will continue construction oversight and provide updates at future board meetings; facility and budget implications arising from the change order and pilot projects will be addressed in forthcoming finance reports.