Travis Unified certifies Measure R results and outlines priority Measure R projects, oversight committee and initial contracts

Travis Unified School District Board · January 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board certified Measure R election results, authorized the formation of a citizens’ bond oversight committee, approved contract steps for Golden West classrooms and discussed a tiered facilities master plan prioritizing security, HVAC/roofing and urgent DSA‑mandated stadium/ADA work.

The board certified the Measure R election results (staff reported an approval margin the presentation listed at about 60.72% yes) and approved a resolution to establish the seven‑member Citizens’ Bond Oversight Committee. The superintendent and up to two board members will help conduct initial interviews of candidates for the committee.

Staff outlined the facilities master plan and a tiered list of projects compiled by consultants and the facilities advisory committee. Priority (tier‑one) projects include security upgrades (fencing, cameras, controlled entries), urgent HVAC work such as boilers and chillers at multiple sites, roofing and exterior repairs, ADA and DSA‑required stadium repairs, and safety‑driven playground surfacing work. Staff said some projects will be advanced in the first bond sale and that sequencing will try to limit disruptions to athletics and school calendars.

The board approved lease‑leaseback preconstruction services and selected Excel Construction (with preconstruction/manufacturer Timber Quest) for Golden West classroom additions; staff explained the lease‑leaseback method permits evaluation of contractor experience and capacity rather than selecting by price alone. Staff noted DSA site and pad requirements that could affect final GMPs and that a guaranteed maximum price will be submitted to the board when available.

Board members asked for transparency and a public bond website; staff said they will publish project lists, COC information and progress updates as projects begin. Staff also said they are pursuing state reimbursement where possible.

What happens next: The board will receive GMPs and project schedules for each tranche; staff will solicit and review COC applicants and begin priority procurement and DSA submittals.