Phase-one work nears finish; parking, clinic and conference-room reopenings set in April

Building Project Committee · April 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Committee heard that phase one work is largely complete: the Justice Center east lobby reopened March 9; conference room will reopen April 8; employee clinic will reopen April 20; facilities staff move scheduled April 30; final phase-one IT move targeted May 18; parking-lot paving will be completed over a brief scheduled closure and a detailed phase-one punch list walk-through is set for April 14.

Staff reported the building project is approaching completion of phase one and detailed near-term milestones for users and staff.

The presenter said the Justice Center east lobby and security checkpoint reopened March 9; the conference room behind the boardroom "reopens April 8th" and the employee health clinic is scheduled to reopen on Monday, April 20. Facilities staff are scheduled to move across the hall by April 30 and IT moves are tentatively planned for May 18, the presenter said.

Work on the parking lot will proceed over about four weeks, staff said, with the final three days requiring temporary fence movement for paving; portions of the lot will remain open during most of the work and ADA access from the sheriffs office will be preserved. Staff also said bollards, pole bases and seven new light poles are being installed and sidewalks will be poured this week.

Environmental surveys were completed for phase-two and phase-three spaces, allowing abatement work to proceed as contractors are cleared to begin; staff said many asbestos-related costs came from materials (mastics under carpeting and pipe wraps) discovered only after demolition. A detailed punch-list walk-through for phase-one areas was scheduled for April 14 to identify outstanding items for correction.

Staff offered tours of phase-one areas for committee members and encouraged coordinations for either individual tours or a posted group tour; committee members were asked to coordinate times with staff.