Escondido library renovation nears completion; move‑back targeted for mid‑June
Summary
City and library staff said major renovation work is finishing at the Escondido Public Library: roof and plumbing are complete, painting and remaining electrical work are finishing soon, and staff expect to begin moving back in mid‑June with a likely reopening in mid‑July.
Get email alerts on the Library Renovation topic
No spam. Unsubscribe anytime.
Robert, presenting the library renovation update, said crews will finish the roof “100% complete by end of day tomorrow,” and that plumbing is complete though fixtures still need installation. He reported the first floor electrical and lighting are about 80% done and the second floor about 60% complete, with remaining work delayed by fixture deliveries. Drywall is finished and painting is expected to be wrapped up by mid‑next week.
Robert said door frames are installed but the doors themselves are scheduled later in the sequence, and that second‑floor windows are almost entirely in while first‑floor windows are about 20% installed. He told the board the ADA path of travel concrete at the building entrance has been demolished and will be replaced within weeks.
Furniture, fixtures and equipment will arrive on a staged schedule: book stacks are expected in early May and general furniture at the end of May, Robert said. He added that climate‑control contractors will begin work in April and expect about two months to finish, which would clear the final major contractor work in early June and allow staff time to move back into the main building.
“The roof will be 100% complete by end of day tomorrow,” Robert said. He also described a transition plan that is currently in the city manager’s office for approval and pledged to circulate the plan to trustees once it is approved.
Board members discussed logistics for the move, noting the likely need for a short closure for the physical move and a multiweek re‑opening ramp. The board scheduled a walkthrough of the site on April 9 for trustees to view progress before the council presentation and to help finalize move logistics.
The update also covered technology planning: library staff and IT conducted a walkthrough to identify Wi‑Fi access‑point placement for newly created smaller rooms, and IS staff will meet vendors next week to finalize equipment placement.
Next steps: the board will finalize and route the transition timeline through the city manager’s office and bring a slide deck to City Council as part of a larger boards‑and‑commissions update; trustees will preview the site at the April 9 walkthrough.