Council approves two contractor payments for WWTF forcemain and lift station project
Summary
The Barron Common Council unanimously approved two contractor payment applications from Market and Johnson totaling $965,489.23 for the WWTF Forcemain and Lift Station portion of the Lasalle Phase 3 project and heard an update from MSA on project progress.
Get email alerts on the Wwtf Forcemain Lift Station topic
No spam. Unsubscribe anytime.
Teresa Anderson of MSA presented an update on the Lasalle Phase 3 wastewater project and filed two contractor payment requests for the WWTF Forcemain and Lift Station work. Alderperson Pete Olson moved to approve Application for Payment No. 6 from Market and Johnson for $459,879.37; Alderperson Mo Tollman seconded and the motion carried unanimously.
Alderperson Keith Kolpack then moved to approve Application for Payment No. 7 from Market and Johnson for $505,609.86; Alderperson Joe Johnston seconded and the council approved the motion unanimously. The payments together total $965,489.23 and were recorded as approved in the minutes.
The update from MSA outlined contract progression and prompted the council to act on the two payment requests; no recorded objections or conditions were entered on the motions. The council did not specify additional contingencies or retainage in the minutes. The approvals follow the council's routine contract-administration process for public works projects and were entered on the consent of the majority of alderpersons present.
The city engineer/consultant (MSA) remains the project contact for construction oversight. The council's next steps noted in the minutes were routine payment processing and continued project oversight; no separate vote to change contract terms or scope was recorded.