Aztec approves short extension of New Mexico 173 waterline using remaining ARPA funds
Summary
The commission approved a roughly 350-foot extension of the NM 173 water main, reallocating remaining ARPA funds to ensure spending deadlines are met; staff said additional funding and design work remain for later phases.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Aztec City Commission approved the New Mexico 173 waterline project Nov. 18, authorizing a roughly 350-foot extension as part of a multi-phase buildout and reallocating remaining ARPA funds so the city meets federal obligation deadlines.
Staff explained the project is the latest phase following a 2022 $1.5 million grant that funded earlier construction and a subsequent ~1,300-foot stretch installed last year. The current addition, described as approximately 350 feet, was presented to use remaining ARPA obligations because other items (such as tank site work) would not be spent before the federal deadline.
Commissioners asked about the line’s location and capacity and whether the extension would serve a small tank at the south end of a development; staff said the tank is smaller than ideal for the area and that completing every available foot of pipe now reduces future work and cost.
"Every foot we can do of the water line is just one less foot we have to do for future funding," Ruben said.
Commissioners voted to approve the project after clarifying that ARPA reallocation and grant rules permit moving unobligated funds to already approved projects.
Staff said the extension is a straightforward construction phase that will be folded into broader transmission and distribution planning for the South Aztec area; longer-term construction will require further funding.