Lafayette City board approves demolition contract for former Hannah Center to make way for Right Steps daycare
Summary
The Lafayette City board approved a $36,900 demolition contract with Poisel Construction for 1201 North 18th, saying the site will be cleared for the new Right Steps daycare; the board also authorized an immediate notice to proceed.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
Jason Burke, Lafayette City building commissioner, told the board it is recommending a $36,900 contract with Poisel Construction to demolish the former Hannah Center at 1201 North 18th so the site can be developed for a Right Steps daycare center.
Burke said the city solicited three bids: Poisel Construction at $36,900, Crawl Earthwork at $41,500, and Snyder Construction withdrew. "This contract with Poisel is in the amount of $36,900, and we are recommending your approval," he said. The board moved, seconded and approved the contract by voice vote.
Following the contract approval, city staff recommended — and the board approved — an immediate notice to proceed to Poisel Construction so demolition can begin. The board recorded the votes by voice; no individual roll-call tallies were provided.
The action clears the parcel for the Right Steps daycare project; the meeting did not include additional details about the daycare's timeline, funding or construction schedule. The item was presented during the engineering/new business portion of the agenda and passed without further questions.
The meeting then moved on to other business and later adjourned.