Carbondale pool on schedule; trustees told TCO was issued, change orders small and acoustics may need study
Summary
Project manager reported a temporary certificate of occupancy issued Feb. 5, pool plastering targeted for April 1, the project remains within budget, and trustees agreed to test rooftop heat-pump noise before committing to up‑front mitigation (estimated $17,500–$22,000).
Carbondale trustees received a construction update on the town’s new aquatic center, where the project team said the temporary certificate of occupancy was issued Feb. 5 and pool plastering is slated to begin April 1, weather and material deliveries permitting.
Project staff said most interior systems and finishes are in place, landscape work is on the schedule, and the overall project budget remains steady. The report listed potential change orders (PCOs) totaling roughly $39,644 that are under review and said the remaining pending balance is about $188,729. Staff explained…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat