Council approves wastewater pay application as engineer says plant is nearly complete
Summary
Council approved pay application No. 25 for the wastewater treatment plant as project engineer Emily Limebball told the council major equipment is installed, the screw press is running, and final systems work and a SCADA upgrade remain; punch list work is scheduled for April 15.
VINTON — The Vinton City Council approved payment application No. 25 for the city’s wastewater treatment plant project March 26 after an on-site construction update from project engineer Emily Limebball of Bester and Kim.
Limebball told the council that most major equipment is installed, the headworks are operating, and the screw press had come online. She said one pump has a manufacturer issue but the system is designed to operate with a pump out of service, meeting Department of Natural Resources requirements. "We've had a couple…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat