Kalamazoo City director flags higher baseline water production, plans to consolidate wells and expand iron treatment

Kalamazoo City Utility Policy Committee · March 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Public Services Director James Baker told the Utility Policy Committee that long-term production trends show higher baseline flows, the city plans to retire many small wells and drill fewer higher-capacity wells, and staff will expand iron treatment to reduce water-quality complaints.

James Baker, Kalamazoo City Public Services Director and city engineer, presented the director's annual water-system and asset-management reports to the Utility Policy Committee on March 12, 2026, saying the system's long-term baseline flow is higher than in past decades and that drought-era spikes around 2007 and 2012 still appear in a 20-year production chart.

Baker said these higher baseline flows, together with episodic drought spikes, inform capital planning: "Those spikes in 2007 to 2012 were water production during drought years," he said, and the city must size treatment and production capacity to meet both normal- and high-demand years. He told the committee the city is programming investments in well fields and station production capacity to address the trend.

The director outlined operational priorities. Staff track water-quality complaints by district and report most issues as iron-related in this groundwater system; only two of the city's 13 treatment plants currently have iron removal. "We are increasing our iron treatment in the system," Baker said, noting a project that consolidates two plants (Stations 5 and 14) into a single treatment plant to expand treatment capacity.

Baker described the city's meter changeout program as roughly 30% complete and called out a steady annual progress rate of about five percentage points, which would reach roughly 50% completion by the end of 2027 if current rates hold. He also said 2025 was an unusually high year for water-main breaks, with about 134 breaks recorded; early 2026 counts are lower so far.

On asset strategy, Baker said the utility plans to consolidate lower-capacity wells: many existing wells average 350'550 gallons per minute (gpm); the plan is to abandon about 30 smaller wells and replace them with roughly 10 new higher-capacity wells (on the order of 1,000'1,200 gpm each) to reduce the number of assets requiring rehabilitation and to provide a wider hydraulic range using variable frequency drives.

Baker noted the utility draws from several aquifers and that aggregate aquifer capacity is large relative to current pumping capability: "If we took all the aquifer capacity of our system it's something near 150 million gallons a day," he said, while system pumping capacity is about 40 million gallons a day. He cautioned that station siting and land availability constrain where new wells can be developed.

The committee asked whether the station consolidation and new plant would change current production numbers; staff said construction is under way but the new plant will not affect system production statistics until roughly 2029'2030 when it comes online.

Why it matters: the combination of rising baseline demand, continued new connections in expanding townships, and concentrated water-quality concerns in outer districts drives the city's capital priorities. The utility intends to focus capital and operational work on iron treatment, well rehabilitation and consolidation, meter replacements, and cast-iron main replacement to reduce breaks.

Next steps: staff will continue design and permitting work for well rehabs and the station consolidation; the committee requested more detailed residential versus non-residential water-use breakouts from audit tables and confirmed the director's report is available for commission review if the council requests it.