Budlong Pool complex: pool house finished, plastering awaits warmer temperatures; city to absorb $62,830 of unforeseen excavation work
Summary
Public Works director reported the Budlong Pool house interior is complete, pool walls and gutters are installed and plaster/tile work is pending a sustained 50°F minimum; contractor encountered unsuitable peat that required removal (about $89,000 total), with the contractor absorbing about $27,000 and the city responsible for approximately $62,830. The committee asked for weekly progress updates toward a mid‑June completion.
Public Works Director Frank Caro updated the public works committee on Budlong Pool construction, saying the pool house interior (locker rooms and bathrooms) is complete and most pool structural work is finished, but plaster and tile remain pending until weather permits.
"The pool house has been completed," Caro told the committee, adding that the pool walls and gutters are in place and that…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat