Council approves change order for 2025 street improvements; Williams Lane chosen for pilot overlay

Minnetrista City Council · June 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved Change Order #1 to the 2025 street improvement project, adding fabric on Windridge Trail and authorizing resurfacing options for Williams Lane (estimated $36,000) including an ultra‑thin bonded product pilot to extend pavement life.

The Minnetrista City Council on June 2 approved Change Order #1 for the 2025 street improvement project (City Project 01‑25), adding minor geotextile fabric work and authorizing resurfacing of Williams Lane.

Staff member Spelski said the change order covers two items: fabric that helps prevent silt pumping on Windridge Trail (original estimate about $3,400, but actual quantity used was less) and a resurfacing option for Williams Lane. Spelski said Williams Lane has a pavement condition score of 32, placing it in poor condition, and that staff asked Aztec (the contractor on this year’s contract) for a price to overlay the street. The overlay price provided was just over $36,000. As an alternate, staff described an ultra‑thin bonded product — a polymer‑modified surface applied as a thin lift — that can reduce reflective cracking and extend service life; staff noted it is more labor‑intensive to place but has performed well on previous local projects.

Council members asked about drainage and whether Williams Lane has enough traffic to justify a pilot; staff answered that the street drains to a roadside ditch and the project has sufficient road‑fund resources. Kathleen Revkin moved to approve the change order and Peter Vicky seconded; the motion passed 5‑0.

The approved change order remains a maintenance/overlay action and is not a reconstruction project; staff said full reconstruction would be considered on a different timeline tied to water main extension needs and capital planning.

The council moved on after approval; no additional amendments were made at the meeting.