Council hears $22.3 million all‑in estimate, schedule for new Minnetrista water treatment plant

Minnetrista City Council · June 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City engineering and consultants told the Minnetrista City Council the proposed water treatment plant will likely cost about $19 million to construct and roughly $22.3 million all‑in; staff plans to finalize 100% plans in June, advertise late June, open bids late July and begin construction this August with completion expected in fall 2027.

The Minnetrista City Council on June 2 received a detailed design, cost and schedule update for the city’s planned water treatment plant.

Aaron Vulmer, the project presenter, showed interior and exterior renderings, explained process flow (filters, reclaimed tanks, clear well, aeration), and outlined redundancy and capacity. He said the filters are sized so that if one is taken offline for backwash the remaining three can treat about 2,100 gallons per minute and the pumps are sized at roughly 2,800 gallons per minute to meet distribution needs.

Vulmer addressed technical questions about iron and manganese treatment and disposal, saying the settled material remains liquid and “we kind of accumulates over time and then we pump that out into the sanitary sewer.” He also…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans