Skatepark backers cite $750,000 state grant and ask Brainerd City park board for $200,000 match
Summary
Proponents of a 15,000‑square‑foot Memorial Skate Park told the Brainerd City park board they have $870,000 assembled — including a $750,000 state skate grant and $120,000 in local fundraising — and asked the board for a $200,000 match; board members expressed strong support but said current capital funds are not available and directed staff to meet with proponents and return with options.
Get email alerts on the Recreation Infrastructure topic
No spam. Unsubscribe anytime.
Proponents of a Memorial Skate Park told the Brainerd City Park Board on Tuesday that a state skate‑park grant of $750,000, combined with about $120,000 in local fundraising, leaves the project roughly $200,000 short of the board’s preferred budget to include lighting and other amenities.
"We received $750,000 grant from the state," Jake Renker of the Lakes Area Skatepark Association said during the board’s discussion, adding that his group has raised about $120,000 and is seeking a $200,000 contribution from the park board to reach a budget in the $1.0–1.2 million range depending on lighting choices.
The request followed staff remarks that a 2025 bonding bill had allocated $750,000 for construction and that the city must submit a deed application and meet state requirements to access the bonding funds. Paul Forsane of the nonprofit City of Skate, which administered the state grant program, described the grant and recommended a design‑build procurement approach "to streamline the process and assure a higher‑quality project." He said the state program favors communities that can demonstrate local support and some matching investment.
Renker presented three funding/lighting options: a full six‑fixture sports lighting package that would raise the project cost to about $1.2 million, a two‑light package plus conduit for future lights (about $1.1 million), or installing only conduit now for future lighting (about $1.0 million). He said the association hopes to begin construction in 2027 if funding and approvals align.
Board members praised the fundraising and the state grant but repeatedly said the city’s capital budget is constrained. One board member noted existing commitments — parking lot conversion, playground repairs and other capital needs — and said, "we just don't have the money" to make a one‑time $200,000 commitment this year. Members suggested alternatives such as phasing the project, pursuing additional private fundraising, asking the council for staged capital support in future budget cycles, and exploring lower‑cost lighting through the municipal utility as an interim solution.
Rather than commit funding on the spot, the park board agreed it would be prudent to schedule a staff meeting with City of Skate and the skatepark association to explore cost‑reduction options, potential partnerships (including with the municipal utility), phasing scenarios and design‑build contracting details. Staff said it would return to the park board with an update next month and recommended completing a deed application once the board and proposers narrow the preferred footprint and approach.
What happens next: staff will arrange follow‑up meetings with City of Skate and the Lakes Area Skatepark Association, explore lighting and phasing options and return to the park board with refined cost and procurement recommendations. No board vote committing city capital to the $200,000 match was recorded at the meeting.