Hinsdale trustees review $1.22 million plan to replace children's pool; construction slated for late 2026
Summary
Trustees heard a first read on plans to replace the Hinsdale Community Pool’s children's activity pool with a zero‑depth, ADA‑compliant design. The project estimate presented was $1,224,500, with construction expected fall 2026–spring 2027 and grant applications underway.
Get email alerts on the Parks Infrastructure topic
No spam. Unsubscribe anytime.
Hinsdale trustees reviewed plans April 14 to replace the village’s children’s activity pool, a project the board described as addressing aging infrastructure and improving safety, accessibility and play features.
Trustee Fischer said the existing children’s pool was last renovated in 1992 and had reached the end of its useful life. Architect Frank Parisi of Williams Architects presented the concept: a zero‑depth entry, wet‑deck play structure with slides and spray elements, a spray tunnel and improved sightlines for lifeguards, all designed to meet IDPH and ADA guidelines.
Project expenses presented at the meeting totaled $1,224,500; staff indicated the figure was slightly over the original budget and that the project will be sent to bid so final costs can be determined. Construction was described as anticipated to start in fall 2026 and finish by spring 2027 in time for the pool season. Trustees said grants are available and that staff will apply for appropriate pool and infrastructure grants.
Neighbor Tapan Desai, who earlier spoke during citizens petitions, told trustees he appreciated the replacement but asked that the village preserve meaningful landscaping along Thurlow Street; staff committed to working with residents on screening and evergreen plantings to soften the view.
Why it matters: The project replaces a long‑used park amenity, updates safety and accessibility, and carries a mid‑six‑figure price tag that will be refined through bidding and grant awards.
What’s next: Staff to prepare bid documents, pursue grant funding, finalize landscaping plans with resident input, and return with bid results and any request for supplemental funds.