Town manager outlines ongoing storm recovery, FEMA process and debris removal
Summary
Town Manager Mark updated the council on storm recovery: FEMA coordination for reimbursement, RFQ for engineering services, bids for ball‑field grading, debris removal including C&D and hazardous waste, and reminders about leaf and white‑goods collection.
Get email alerts on the Storm Recovery topic
No spam. Unsubscribe anytime.
Town Manager Mark briefed the council on ongoing storm‑recovery operations and next steps.
He said the town has engaged FEMA processes and expects typical FEMA reimbursement rates of about 75 percent for eligible costs. Staff is issuing an RFQ for engineering services to help prepare federally and state‑compliant bid specifications; the RFQ deadline was noted as the coming Monday. An element of the recovery (laser grading and dirt work for ball fields) has moved forward to bid and staff will review bids to determine contract awards so the fields can be ready for spring athletics.
Debris removal remains a major operational focus. The county contractor (SDR) has been collecting vegetative debris and will shift crews to construction and demolition (C&D) debris; staff asked residents to file online requests to ensure priority pickup. Mark said hazardous waste (household chemicals and paints) and white‑goods pickup are on the coordination list and encouraged residents to provide photos and addresses when requesting collection to help the county crews find piles.
Mark said town staff continue to monitor private road damage and coordinate with county efforts; he thanked crews for the progress so far and reminded residents to use online forms to report debris for pickup.
No council action was required; this was an informational report.