Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Solar Projects topic
No spam. Unsubscribe anytime.
Ulster County committee approves design funding for solar array aimed at making new emergency communications center net-zero
Summary
The Public Works committee approved SEQR and design funding to develop about 104 kW of rooftop solar plus roughly 310 kW of ground-mounted panels to serve the County’s Emergency Communications Center; staff said tax-credit deadlines and site wetlands narrowed the plan from an earlier multi-megawatt concept.
Get email alerts on the Solar Projects topic
No spam. Unsubscribe anytime.
Ulster County’s Public Works and Capital Projects Committee on April 13 voted to move forward with environmental review and design work for a solar installation intended to power the county’s Emergency Communications Center (ECC).
The committee adopted Resolution 171, designating the Ulster County Legislature as lead agency under SEQR and reclassifying the project as a Type I action after staff said the proposed array comes close enough to a structure eligible for the National Register to require a full, coordinated environmental review. The committee unanimously approved the design authorization (Resolution 172) and contract awards tied to the project.
Why it matters: Staff told the committee that federal investment tax-credit changes and site constraints — including wetlands buffers and substation capacity — prompted the county to scale back an earlier multi‑megawatt concept and focus first on rooftop and targeted ground‑mounted arrays that can be completed in time to capture tax incentives. Deputy Executive Laval told the committee, “there have been some changes to the federal investment tax credit for solar. In particular, it's being sunset.” That timing drove an emphasis on projects that are “ready to go.”
What the county approved: The design authorization covers roughly $340,000 for engineering and environmental work for a ground‑mounted component of about 309–310 kilowatts. Staff said the ECC rooftop already includes about 104 kilowatts of planned rooftop solar. Committee materials and staff remarks put the anticipated total buildout cost at about $2,492,000, with investment tax credits and state incentives expected to reduce the county’s net exposure to roughly $1.7 million.
Technical and siting limits: Planning and engineering staff described two constraints that narrowed the project’s footprint. First, DEC mapping and new wetlands jurisdiction added 100‑foot buffers around wetlands on the Parades/Paradise Lane site, removing acreage once assumed available for a larger array. Second, interconnection and substation capacity limit how much generation can be added without upgraded grid infrastructure. Staff said the ground‑mounted portion would be located behind the meter to serve the ECC when the building consumes electricity and export excess generation to the grid.
Battery storage and related issues: Committee members pressed staff on battery storage and local emergency-service impacts. Dennis from planning said battery storage remains eligible for tax credits and could be pursued, but cautioned that any battery project would likely be privately developed and taxable. A committee member raised concerns about fire‑district costs and emergency‑response burdens; Dennis said literature and local discussions have not indicated large insurance or cost impacts from comparable solar projects but that battery storage has generated more discussion among planning boards. One member cautioned against SEQR “segmentation,” urging that any battery storage element be evaluated as part of the overall project if it will be proposed.
Costs, energy modeling and payback: Staff circulated energy modeling showing the ECC, with rooftop solar and other efficiency measures, could see modeled energy costs of roughly $89,843 per year; staff estimated a straight payback of about 20 years under current assumptions (16 years with a 3% annual utility-cost escalation). Officials emphasized utility prices’ volatility and framed the solar installation as one element in a broader goal of making the ECC a net‑zero facility.
Procurement and schedule: The committee also approved Resolution 174, a contract with Amoresco, Inc., to support project work; staff confirmed vendors and procurement partners are aware of tax-credit schedule constraints, including deadlines referenced in contract schedule materials. Committee members asked staff to circulate the Amoresco proposal and other supporting documents.
What happens next: Because the project is now a Type I SEQR action, the county must complete a full Environmental Assessment Form and coordinated review with involved agencies before construction. Design funding will allow site engineering, permitting and final procurement; further decisions about batteries, larger site build‑outs or alternate ownership structures will return to the Legislature as proposals are refined.
The committee approved the SEQR designation, the design authorization and related contracting steps by voice vote; the measures passed unanimously.

