Commission approves $79,414 reduction to rehabilitation and lighting project under AIP grant
Summary
The commission approved Change Order No. 1, reducing the runway rehabilitation and lighting project by $79,414.25 under AIP grant AIP3‑40‑00003‑0‑2024; savings will be allocated consistent with grant funding and sent to city council for ratification.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Commissioners approved a change order that reduces the total contract amount for the airport rehabilitation and lighting project by $79,414.25 under FAA/AIP grant AIP3‑40‑00003‑0‑2024.
Staff explained the project costs came in lower than bid estimates, producing overall savings. Because a portion of the project is grant‑funded, the city will realize its share of the savings proportionately; staff will forward the approved change order to the city council for ratification and filing.
The commission took a roll call vote and the change order passed. No member voiced opposition during the recorded vote; staff characterized the reduction as a positive result of competitive bidding and efficient contracting.
The commission directed staff to file the change order with council and to confirm the adjusted funding distribution consistent with the grant terms.