Board approves video scoreboards and a student curriculum tied to ad revenue
Summary
Trustees approved purchasing video scoreboards (purchase recommended over lease), with administration saying the package includes a student curriculum and ad-revenue assistance; costs were estimated at about $185,000 (with optional upgrades) and will be covered from fund balances. Additional infrastructure costs were noted as not included in vendor quotes.
Get email alerts on the Facility Equipment topic
No spam. Unsubscribe anytime.
The Columbia CUSD 4 Board approved purchasing digital video scoreboards for the districts multipurpose field and gymnasiums, with staff recommending purchase rather than a lease and to pay from current fund balances.
Administration described two vendor options: the districts incumbent (Nevco) offered to match local pricing, while a local vendor proposed lower pricing plus a curriculum package that would train staff and, eventually, students to operate the boards as a hands-on course or CTE pathway. The district would initially rely on vendor assistance with advertising sales and on a revenue split that could be 50/50 while the vendor builds out sales, moving to a larger share for the district in later years.
Cost details discussed in the meeting included a core package for field and gym boards estimated around $185,000 (the district cited a $200,000 figure for the field plus an $85,000 optional 10-by-9 back-facing board). Leasing remained an option at roughly $40,000 per year depending on configuration; staff recommended purchase to maximize long-term revenue and return on investment. Administration also warned trustees that vendor quotes did not include electric or fiber infrastructure work and that the first year could be a deficit year for operations before ad revenue ramps up.
Administration said the vendor estimated local ad revenue potential at roughly $100,000 per year once sales were established, but staff emphasized revenue projections depend on local sales activity, contract terms and how the district phases-in responsibility for ad sales.
The board moved and approved the purchase by roll call. Trustees discussed implementing the curriculum as a multi-year plan beginning with a train-the-trainer model so staff could teach students to operate scoreboards and build a sustainable program over time.
Next steps: administration will finalize contract terms, confirm whether sound-system upgrades are required and report back on total infrastructure costs before installation.