Commissioners approve additional funding to complete Rangely chip-seal program after higher-than-expected bids
Summary
Road & Bridge reported a higher-than-budgeted bid for the 2026 Rangely chip-seal project (34.46 miles). Commissioners approved a supplemental appropriation to complete the planned work rather than delay preservation, noting deferred maintenance would increase future costs.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
Road & Bridge staff told commissioners that the 2026 Rio Blanco County chip-seal project for Rangely came in about $222,000 over the planned $1.5 million budget. Staff said the county planned to chip-seal 34.46 miles in Rangely this year; mobilization economics mean it made sense to do the full scope at once rather than splitting work across mobilizations.
Commissioners discussed possible internal savings from a separate pavement 'mag' (mastic) program; staff said some savings occur in personnel and equipment by performing mag work in-house but the product purchase and other line items were already budgeted. Commissioners weighed the cost of deferring work (which would lead to more costly pavement replacement) against the need to find supplemental funds. Given the county’s fund balance position and deferred-maintenance risk, the board approved a supplemental budget appropriation to cover the additional chip-seal cost and authorized staff to proceed with the vendor selection and award process.
Road & Bridge indicated chip-and-seal frequency is typically every seven years for roads and that the current bid reflected rising unit costs. Staff will process a supplemental budget and return with final contract documentation.