Westerville board approves HVAC, roof, restroom and facade contracts totaling roughly $4.2 million

Westerville City School Board of Education · April 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved FY26 HVAC contracts (about $3.7M, bond-funded), a $29,600 restroom-partition upgrade at Central High, a $267,830 roof repair at North High and a $149,212.81 facade-restoration contract for three middle schools.

The Westerville City School Board approved multiple facility contracts at its April 6 meeting, including a multi-package HVAC project, restroom-partition upgrades, roof repair and facade restoration.

Mr. Swartz presented the FY26 HVAC solicitation and explained the project is split into bid packages and alternates with a total cost just under $3.7 million and an August 10, 2027 completion target. Contracts include Deborah Kumble Inc. (low qualified bidder for multiple packages; $1,881,000), H&A Mechanical ($1,257,000) and Premier Energy Services (building-controls scope procured through Omnia Partners). The administration noted the HVAC work is bond-funded.

The board also approved a $29,600 permanent-improvement contract with Ultimax Inc. to raise stall partitions in one restroom group per floor at Central High School, citing student concerns about privacy and decency; work is scheduled for completion Aug. 14, 2026.

Additional approved projects included a North High School roof-repair contract with Garland DBI Inc. (proposal via Equalis Group) for $267,830 and a facade restoration contract with Weatherproofing Technologies Inc. for $149,212.81 covering Longfellow, Genoa Middle and Heritage Middle schools (consortium procurement through META). Completion windows for summer 2026 were discussed in each presentation.

Why it matters: The approved contracts address deferred maintenance and student-expressed concerns about privacy in older facilities. Administrators noted bond funding covers larger projects; smaller permanent-improvement funds cover other upgrades.

Next steps: Contracts are scheduled for summer work; staff will monitor procurement schedules, material lead times and provide updates as construction progresses.