City advances pavilion schematic design; ballpark renderings, phased bidding and fundraising discussed

Detroit Lakes City Council · September 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Architects and staff told the council schematic design has started for the pavilion and a community open house will be Oct. 7; Washington Ballpark renderings show a renovated grandstand, improved ADA access, and a two-phase bidding approach (building components first, turf/field later) while fundraising outreach continues.

City staff and consultants updated the council on design progress for a new pavilion and improvements at Washington Ballpark.

Brian, the pavilion steering-committee lead, said the project has moved toward schematic design and the team will hold a community open house on Oct. 7 with follow-up engagement the week of Oct. 11. He said the team will then submit schematic materials to the State Historic Preservation Office before moving forward with construction-phase pricing.

Sean Senkll of JLG Architects said schematic design work has begun to establish the pavilion site plan, floor plan, exterior materials and structural systems; he noted geotechnical work shows poor soils on the site and that the design team is working on cost-effective structural options.

On Washington Ballpark, city staff presented 3D renderings showing a new concession stand and plaza, higher netting to protect the concessions area, improved ADA ramps and a revised grandstand layout. Staff said they intend two bid packages: a building package (grandstand, dugouts, concession stand) and a later civil package for field improvements and turf.

Kelsey reported ongoing fundraising (a mailer to about 600 addresses was sent; initial responses are small but pledges exist) and said the project may rely on a mix of community fundraising and project funding once bids or cost estimates are refined. Councilors asked about the turf package and staff said the field/turf work will be bid separately after the building components.

No final decisions were made; staff will continue community outreach, refine schematic drawings and update the council on costs and fundraising progress.