Commission finds Panino (Penino) solar farm in compliance after weed and fire‑response actions

San Benito County Planning Commission · April 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission found the solar facility in substantial compliance with its development agreement after the operator improved weed management, conducted fire‑response training with Hollister Fire, filed an ITP amendment with CDFW and advanced a community outreach plan.

The Planning Commission unanimously found the Panino (referred to in materials as Penino) solar project in substantial compliance with its development agreement at the May 12 meeting after staff, the operator and fire officials reported continued remediation and mitigation work.

RWE/asset management representative Shannon Ammonet said the company is coordinating with the California Department of Fish and Wildlife and has filed an amendment to its Incidental Take Permit seeking authorization to use mechanical measures (mowing) and limited herbicide in some areas. Ammonet said the company has hired outside consultants, joined the San Benito Chamber of Commerce to strengthen local ties and posted site‑staff positions to maintain on‑site measures.

Hollister Fire Marshal Charlie (Bedo) reported he conducted fire‑response training with on‑site staff, that a fire‑response plan and an Emergency Action Plan (EAP) have been prepared, and that crews had improved weed management despite regrowth caused by recent rains. He said the site now has ongoing maintenance and planned follow‑up inspections.

Commissioners noted the history of environmental review and mitigation on the project, including prior litigation and a 2017 settlement that resulted in splitting the original project footprint and creating a mitigation land endowment. Based on the recent updates, the commission voted unanimously to adopt a resolution finding the project in substantial compliance with its development agreement and directed continued monitoring of fire and habitat mitigation measures.

Next steps: the operator will continue to work with CDFW on the ITP amendment, maintain the weed management and fire‑response program, and report back to the county as required by the compliance schedule.