Board reviews renovation change orders, credits for high‑school project and stadium improvements

Cornwall-Lebanon School District Board of School Directors · April 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Buildings and Grounds staff detailed multiple change orders tied to Cedar Crest High School renovations and stadium work, including plumbing and electrical credits (totaling tens of thousands of dollars) and a $70,000 annual Siemens automation services agreement to be approved next week.

District buildings and grounds staff updated the board April 13 on pending change orders for the Cedar Crest High School renovation and related stadium improvements and said the items will be placed on the consent agenda for approval at the board’s next meeting.

Mrs. Hentz explained several individual change orders: a $1,499 change order (general contractor, change order #9); a plumbing credit of $33,633 for an unnecessary air compressor; a mechanical piping replacement (phase two) costing $43,493; and multiple electrical vendor changes that produced a $90,000 credit, leaving a remaining credit of $65,694 to offset other pending orders. Roofing flashing work added a $8,529 change order. For the stadium, a consolidated change order (number six) totaling $27,684 covers rock retaining walls, an additional ramp railing and keyed thumb‑locks; presenters said these costs are covered by contingency funds.

Staff said change orders are reviewed by the district’s construction manager (Fidevia), architects and engineers before coming to the board and that the projects remain on schedule with an anticipated stadium completion around the end of July and commencement still planned for the stadium. Mrs. Hentz also presented the district’s annual Siemens automation services agreement (one year) covering four of six buildings plus the stadium and the recently added Falcon connector, with a contract amount of about $70,000; administrators said this covers remote access, data backup, and 24/7 remote support with on‑site visits as needed.

What the board will vote on: the listed change orders, the stadium change order, and the Siemens one‑year services agreement are scheduled for formal approval at next week’s meeting. There were no formal votes on these items at the April 13 work session.

Context and fiscal note: presenters said contingencies and prior credits cover the listed change orders; district staff emphasized review by construction managers and architects to vet the work.