Council debates Town Square shade structures, opts not to add shade package now
Summary
After extended discussion about sequencing, contingency exposure and competing downtown priorities, council voted not to proceed with a $153,281 shade‑structure package for the Town Square project and asked staff for a full accounting of Embellish grant spending before pursuing additional enhancements.
Get email alerts on the Parks topic
No spam. Unsubscribe anytime.
Council members debated whether to approve a $153,280.88 optional shade‑structure package for the Town Square (Embellish/downtown) construction. Staff said installing the shades now would be more cost‑efficient because foundations could be installed during the primary construction sequence, while other council members preferred deferring the expense to gauge grant expenditures and prioritize other downtown needs.
The shade package vendor (via Sourcewell cooperative purchasing) was presented as a timely add‑on to avoid later rework and mobilization expense; opponents cited competing needs across the downtown area, long‑term maintenance and the project’s 10% contingency and other budget uncertainties. Council ultimately approved a motion to not add the shade‑structure package at this time and asked staff to return with the current grant expenditure status and remaining contingency details before considering additional enhancements.
What’s next: Staff will provide current spending-to-date for the Embellish grant, breakdown of contingencies and recommended priorities for remaining grant funds. Council members signaled interest in allocating future embellishment dollars to other downtown needs if warranted.