Commission hears progress on large solar project and Central Middle School interconnection review
Summary
Mr. Keith said a larger solar panel project cleared planning and zoning special‑use permit requirements and council approvals; staff will begin contract drafting in mid‑February and review a Central Middle School interconnection agreement.
Get email alerts on the Solar Project topic
No spam. Unsubscribe anytime.
Mr. Keith told the commission that a proposed large solar‑panel project recently cleared planning and zoning, which approved a special‑use permit, and that the council approved related items the previous evening.
He said project applicants are completing their application and that staff — including the commission attorney and operations staff — will begin drafting contract language, possibly in mid‑February, and will also coordinate an MMPA contract. "So from that standpoint I think we're in good shape . . . we'll start working on the contract that that we've got Ron and Todd and others looking at," Mr. Keith said.
Separately, staff reported they are reviewing an interconnection agreement for Central Middle School's solar installation and expect to provide comments back to the applicant.
No formal approvals of contracts or interconnection terms were made at the Jan. 21 meeting; the discussion was an operational update on permitting, council approvals, and next steps for contract preparation.