Council approves reallocation to repair Steven Park playground after storm damage
Summary
Following storm damage that revealed the playground required original‑manufacturer parts and was uninsured for equipment loss, council approved reallocation of fence funds to repair Steven Park playground and restore warranties so the playground can reopen safely.
Get email alerts on the Parks topic
No spam. Unsubscribe anytime.
After a February storm damaged playground equipment at Steven Park, Public Works Director Jimmy Charles told council the structure could not be repaired with off‑the‑shelf fasteners and needed original manufacturer components to preserve warranties. Kelsey (town staff) said the playground equipment had been removed from equipment coverage at least ten years ago and was only covered for liability, leaving the town responsible for replacement costs.
Council moved to reallocate fence funds to cover the repairs so the playground could be returned to service; the motion (2026‑9) passed unanimously. Staff said repairs could begin shortly after receiving parts from the manufacturer and that they would pursue reinstating insurance coverage for updated equipment where possible.
Why it matters: The decision restored a neighborhood amenity and preserved warranty protections on repairs, but it also highlighted a gap in asset coverage that staff said they would work to correct in future budgets and insurance updates.