Committee approves a slate of drainage, right‑of‑way and grant items

Charleston City Public Works Committee · March 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The committee approved multiple easements, contract awards and grants — including a $10.25 million construction contract for South Windermere, a $5 million state resilience grant for Cooper River drainage and a $1 million NFWF design grant for New Market Creek — by voice votes.

Charleston City committee members approved a series of infrastructure and grant items, clearing the way for construction, maintenance transfers and preliminary design work across several drainage and public‑works projects.

The committee voted to accept and dedicate multiple rights‑of‑way and easements, including two Johns Island multi‑use path segments and associated maintenance agreements that staff said place some responsibility for upkeep on the city in SCDOT right‑of‑way. Mr. Booty described E1 as "a multi‑use path out in Johns Island" and the committee combined E1 and E2 for approval.

On the South Windermere drainage project the committee approved the $10,250,000 low‑bid construction contract with Lowcountry Site Work and separately authorized $426,000 for construction engineering and inspection services. Staff also presented a corrected cost‑share with Charleston Water Systems that sets the city's contribution at $1,587,245.92 and the utility's contribution at $2,359,254.08 after a spreadsheet error was discovered; the committee approved the correction.

The committee accepted a $5 million grant from the South Carolina Office of Resilience to fund downstream components of the Cooper River drainage improvement project, and accepted a $1 million early‑design grant from the National Fish and Wildlife Foundation for New Market Creek restoration with a city match of $500,000 drawn from the Cooper River Bridge TIF.

Members also approved a construction budget update for outfitting the MUSC pump station, which staff said carries an estimated total cost just under $12 million with an anticipated Army Corps contribution of $4 million and a city contribution of just over $8 million. Staff said MUSC will provide necessary easements and construction cooperation but is not a direct dollar contributor.

Other approvals included multiple drainage easements in Ardmore/Palmetto Ford, a piping solution at 1223 Foushee Way to help an elderly resident access a mailbox, a restrictive covenant requested by SHPO for the Angel Oak adjacent park site, and a water‑taxi dock relocation for Waterfront Park for which Salmons provided a $706,391 quote (the city would reimburse half, $353,195).

Most items were approved by voice vote after staff presentations and brief questions. The committee did not record individual tallies in the transcript; motions were typically "moved and seconded" and approved on the voice call.