Board authorizes major appropriation step to keep Bwell behavioral health construction on schedule

San Joaquin County Board of Supervisors · April 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

To meet grant and schedule deadlines the San Joaquin County Board of Supervisors authorized an approximately $126.4 million appropriation to allow negotiation and execution of an early‑works construction package for phase one of the Bwell behavioral health campus (primarily Building B). Staff said this step is an appropriation timing action and that the full project budget increase will be brought back to the board for approval.

San Joaquin County supervisors on April 14 authorized a substantial appropriation increase—about $126.4 million—to allow county staff to finalize and execute an early‑works construction package for the county’s Bwell behavioral health campus.

County staff emphasized the board action is an appropriations timing step rather than a standalone project budget increase. The request responds to schedule constraints and grant deadlines that require awarding a fourth early‑works package to the county’s design‑build partner to keep Building B on track for service by mid‑2027. Early works packages cover discrete construction phases; package No. 4 is focused on construction of Building B’s core systems and structural work (less final finishes) and is currently estimated at roughly $63.5 million in construction cost as part of broader phase‑one scope.

Project managers said designs for the campus are advanced (approximately 85% design completion for buildings B and C) and that preconstruction coordination (including a detailed MEP model) is being used to reduce field conflicts. Staff told the board that overall project estimates have trended down from higher preliminary prices and that a formal guaranteed maximum price recommendation for core phase‑one work will be presented to the board in June; a separate recommendation for Building A will follow once scope and designs are finalized.

The board approved the appropriation request by motion. County staff will continue negotiations with the design‑build team, execute the early‑works agreement for Building B and return to the board with recommended contract amounts and any requested project budget adjustments.

Representative quote: Ephren Lopez, interim capital projects administrator: “This early works package includes the total construction cost for the behavioral health crisis services center building B (less the final finishes) and is time‑sensitive to meet grant deadlines.”