Assembly approves $41,704 change order to extend seawater pump shafts at KFRC
Summary
The Assembly unanimously authorized change order #2 for contract FY2025-49 to add approximately 10 feet of shaft material to newly purchased KFRC seawater pump assemblies; Manager Williams said the contractor will install the extensions at no markup and the cost covers materials.
The Kodiak Island Borough Assembly voted April 16 to authorize change order number two for contract FY2025-49, addressing a mismatch discovered during pump replacement at the Kodiak Fisheries Research Center (KFRC).
Borough Manager Amy Williams told the Assembly that during installation the new pump assemblies were found to be about 10 feet shorter than the pumps they…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat