Board hears Miller Middle School construction update; schedule and financing steps set

Marshalltown Community School District Board of Education · January 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District project managers briefed the board on updated Miller Middle School designs, a procurement schedule (bid documents released, pre‑bid meetings Jan. 19 and Feb. 4, bid day Feb. 18), and budget status (within the allotted $99 million range). The board approved procedural resolutions ordering construction and scheduling public hearings and approved a $3.63M GEO pre‑levy resolution with one abstention.

Marshalltown Community School District leaders on Jan. 12 gave a detailed update on the Miller Middle School renovation project and approved statutory steps needed to move the work toward construction.

Project staff said the construction documents would be released to bidders the day after the meeting and outlined key procurement dates: two pre‑bid meetings (Jan. 19 and Feb. 4) and a formal bid day on Feb. 18. Staff told the board they plan to return March 2 with contractor recommendations and aim for site mobilization in late March followed by phased demolition and construction in April.

Mitch, a district project manager, described several bid alternates that could be added depending on bid results, including a renovated concessions area, restroom renovations, south courtyard hardscaping and an expanded parking‑lot build‑out. “Some of those will have termination points that we can’t at a certain point, but the goal would be that on bid day we have a good enough bid day that we can start to pull some of those items in,” he said.

Tim, the design consultant, said the construction scope includes historical restoration of the auditorium, a new secured vestibule and a multi‑purpose commons with AV capabilities. The team reported generally strong contractor interest: a pre‑bid outreach event drew more than 40 contractors and additional firms indicated early interest.

Budget and schedule: project documents and the team’s cost packet indicate the program remains within the budgeted range originally allotted for Miller (staff described it as trending within the previously allocated near‑$99 million allowance, subject to alternates and market conditions). The team also said there are about 28 individual bid packages planned for the work.

Board actions and next steps: the board approved two Franklin Field change orders funded from project contingencies, and approved a resolution ordering construction for the remaining Miller bid packages and set a public hearing for Feb. 16, 2026 at 5 p.m. Finance staff explained statutory sequencing for bid approvals and public notice. The project team will circulate bid documents, host the pre‑bid site walks and return to the board with recommended contractors after bids are opened.

Why it matters: Miller is a major capital project for the district; timely procurements and competitive bids determine whether alternates and historical restoration elements can be retained without additional tax or bond increases.

What to watch: the district has scheduled the formal bid opening for Feb. 18 and expects to present contractor recommendations at the March 2 board meeting. The district is also pursuing short‑term GEO bond proceeds as part of a pre‑levy strategy to stabilize tax rates and reduce interest expense.