Board approves $680,000 change order for water treatment plant upgrades

City of Port Washington Board of Public Works · April 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved Change Order 5 for the city water treatment plant, covering items including a vacuum prime system (~$88,000), chemical room modifications (~$122,000) and a major filter media conversion to granular activated carbon (GAC) (largest item, roughly $300,000).

Roger (staff member) presented Change Order 5 to the board for the water treatment plant, with a total value discussed in the meeting of roughly $680,000. Major line items included a vacuum prime system (about $88,000) that was not part of the original design but is necessary for raw water pump priming, changes to the chemical room and relocation/separation of a polyphosphate tank to meet electrical and safety clearances (roughly $122,000), and a change to the filter media to granular activated carbon (GAC) to improve taste, odor and removal of emerging contaminants (the largest single line item, discussed at roughly $300,000). Roger said one smaller line item (~$15,000) resulted from an engineering omission and the engineer will reimburse the city.

Board members discussed the need for corrective changes and safety risk reductions; the motion to approve the staff recommendation passed on a voice vote. Staff invited board members to tour the plant to review work in progress.

Why it matters: The changes address operational and safety deficiencies discovered during construction and will affect the plant’s ability to remove taste/odor compounds and emerging contaminants; the conversion to GAC is a longer‑term water‑quality investment.

What’s next: Staff will implement change order work as scheduled and incorporate reimbursements from the design engineer as discussed.