County project team shifts jail site to Hanigan Road; STV outlines programming, schedule and capacity work
Summary
STV project director Adam Johnson told the J-POP committee the jail-and-Behavioral Care Center project has moved from Ferndale to a Hanigan Road parcel, which reduces permitting and geotechnical work. He said programmers will deliver a draft jail program at the end of April, with a final report expected in August and design starting in September.
Adam Johnson, project director for STV, told the Justice Project Oversight and Planning Committee on April 16 that the county's jail and Behavioral Care Center project has been moved "no longer building in Ferndale. We are now building on Hanigan Road," a change he said will reduce environmental permitting and ground-improvement costs and speed the schedule.
Johnson said STV has completed scenario development and is in a concentrated programming phase. He described a five-week programming exercise that will produce a draft jail program at the end of April for the design-build team to translate into a basis-of-design document. That basis of design will include blocking and stacking diagrams, operational cost and staffing estimates and preliminary…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat