Hagerstown plans Northern Avenue sidewalk replacements; county to pick up ADA ramp work
Summary
The city plans to replace deteriorated sidewalks on Northern Avenue (a school walking route) via a contractor change order estimated at $165,000; Washington County agreed to fund ADA curb ramp improvements at three side‑streets.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City staff recommended replacing failing sidewalks along the north side of Northern Avenue, a route used by two schools, and asked the council to approve a contractor change order to expedite work while school is out.
Engineering manager Jim Bender said the work is unusual because properties benefiting from the repairs lie outside city limits even though the roadway and right‑of‑way are city‑maintained. Staff recommended using an existing curb/sidewalk contractor via change order to keep costs down and to finish construction over the summer; estimated cost is about $165,000. Unspent highway user funds were identified as the proposed funding source.
Washington County’s engineering director told staff the county will contribute funding for ADA ramp upgrades at three side‑street intersections — a contribution staff estimated in the neighborhood of $15,000. Council members flagged the long‑term plan for Northern Avenue and said early repairs reduce the complexity of a larger repaving project that will eventually require full ADA compliance.
Council signaled support for the summer work schedule and asked staff to return with the formal change order for consent‑agenda approval at the next regular session.