Wiseburn board approves developer-fee increase, awards multiple construction contracts and sets sports complex ribbon-cutting
Summary
Trustees approved modest statutory increases to developer fees, awarded contracts for turf and other Measure E projects, and were updated that the Wiseburn Sports Complex will hold a ribbon-cutting next Friday. Several contract awards and budget items passed unanimously (4–0).
Get email alerts on the Facilities And Finance topic
No spam. Unsubscribe anytime.
The Wiseburn Unified School District Board of Trustees on April 16 adopted a routine statutory increase to school facilities developer fees and approved multiple construction and modernization contracts tied to Measure E improvements.
District facilities staff explained the two‑year State Allocation Board adjustment: residential developer fees will rise from $5.17 to $5.38 per square foot and the commercial/industrial rate will increase from $0.84 to $0.87 per square foot, reflecting the statutory index. "This is just standard best practice to make sure that you are adopting a study to show justification for those statutory fees every two years," district staff member Rob said during the public hearing.
The board unanimously approved a slate of contracts and contract amendments tied to recent and upcoming projects, including additional work on the newly completed Wiseburn Sports Complex (added netting and bleachers), the Delair Elementary soccer-field replacement (award ~ $934,000), a Delair TK playground and turf replacement, a Delair flooring and ceiling refresh, and an exterior painting contract for Wiseburn Middle School (piggyback award ~ $799,417.77). Votes on these facilities items were recorded as 4–0 in favor.
District staff said the sports complex is functionally complete with a few long-lead items outstanding (decorative panels, sound-system component and netting). A ribbon-cutting ceremony is planned for next Friday at 5:00 p.m.; the district asked interested community members to RSVP.
Board members also approved personnel and labor arrangements related to the new facility: the board adopted a job description and salary schedule for a facilities attendant position intended to have staff on-site during open hours and events.
Why this matters: The approvals finalize major capital investments funded by Measure E and ensure maintenance/operations plans move forward. The developer-fee update aligns local fees with state statutory changes and preserves the district’s ability to capture fee revenue for future facility needs.