Habitat for Humanity of Cape Cod presented plans for 14 single‑family affordable homes on a 55‑acre property, proposing an advanced nitrogen‑reducing wastewater system and offering to help the town seek state grants to loop a water main that town engineers estimate could cost roughly $420,000 to complete. The ZBA closed the hearing and asked staff to prepare an affirmative draft for April 16.
Get email alerts on the Affordable Housing topic
No spam. Unsubscribe anytime.
Habitat for Humanity of Cape Cod asked the Falmouth Zoning Board of Appeals to approve a clustered 14‑home subdivision on a 55‑acre parcel that would set aside roughly 7.5 acres for housing and preserve the remainder as conservation land.
The proposal, presented by Warren Brody and the Habitat team, would build eight units in the first phase and six in a later phase, use a cluster/open‑space layout to preserve roughly 3.1 acres of contiguous green space, and install an advanced onsite wastewater treatment system aimed at very low nitrogen discharge rates.
Why it matters: board members and neighbors focused on infrastructure and long‑term environmental impact. Habitat’s team said they will install a Nitra advanced treatment system and manage stormwater on site using bio‑retention and infiltration practices. The applicant also told the board it will extend the town water main to approximately the midpoint of the parcel and work with town staff to pursue a state housing infrastructure grant to help the town loop the line the remaining distance — a looping cost the record cited at about $420,000.
Habitat’s representative, Warren Brody, described the project as both an affordable housing opportunity and an effort to protect open space: “We’re using a cluster model so we can preserve green area and still build homes that families can afford,” he said. The team displayed photos of comparable Habitat projects on Cape Cod and described finishes, site grading, and a road cross‑section roughly 22 feet wide that mirrors other recent small subdivisions.
Board discussion centered on three practical issues: sidewalks, parking, and the water main. Several board members pushed back on requiring sidewalks across the site, while others warned that without sidewalks cars and pedestrians would mix on the roadway. Members proposed a compromise of focused sidewalks or pedestrian improvements combined with homeowner association rules. On parking, several members and a resident urged use of low‑cost geogrid or defined gravel strips to prevent turf damage where visitors may occasionally park; the applicant agreed to show detailed strip layout on revised plans.
On water infrastructure, the town’s zoning administrator and board members pressed Habitat to commit to working with the municipality on a grant application. Habitat said it will share documentation and support municipal grant applications but cannot force a town application; Brody said Habitat has already begun working with town staff and will “take whatever efforts are necessary to pursue obtaining a grant for the waterline extension.”
Neighbors and peer reviewers were given the opportunity to raise concerns about sightlines, drainage and monuments; the applicant and their engineer said many peer comments from Beals & Thomas have been addressed or can be made as conditions.
What the board did: after public comment and technical discussion the board closed the public hearing on the Habitat application and authorized the zoning administrator to prepare an affirmative draft decision for review on April 16.
Next steps: the ZBA will review and vote on an affirmative draft decision on April 16; if approved, the draft will enumerate conditions (stormwater and erosion controls, final site plan revisions to show parking reinforcement, and a condition requiring Habitat to support municipal grant efforts to pursue the water‑main loop).