Hubbard County approves $177,235 program-management contract for Reuse Center project

Hubbard County Board of Commissioners · April 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved an ICS Consulting program-management quote of $177,235 for additions to the Hubbard County Reuse Center and a new fabric storage building; the projects are budgeted with $758,000 in MPCA grant funding and preliminary total construction estimates of about $1.1 million.

Hubbard County commissioners approved a $177,235 contract with ICS Consulting (Park Rapids) for program-management services tied to planned additions and renovations at the Hubbard County Reuse Center and a new fabric storage building.

Solid waste staff said the projects are budgeted for 2026 with $758,000 in grant funding from the Minnesota Pollution Control Agency (MPCA) and preliminary construction estimates totaling about $1.1 million (reuse center ~$850,000; fabric building ~$250,000). Stantec (landfill engineering consultant) was solicited but did not submit a quote; ICS was the single bidder. Staff recommended awarding the program-management work to ICS to begin engineering, permitting and bid preparation so the county can meet grant timelines.

The board approved the low quote by voice vote. Staff outlined a timeline: engineering and permitting through June, bidding in July, and construction targeting August through December with a goal to meet a June 30, 2027 grant deadline for eligible work.

Why it matters: The contract starts county work on reuse-center renovations and a storage building funded in part by an MPCA grant. Program management is intended to keep design, permitting and bidding on schedule to satisfy grant requirements.

Next steps: County staff will execute the contract with ICS, begin engineering and permitting immediately, solicit construction bids around July and aim to complete primary construction actions by the end of December, with final project deadlines tied to grant terms.