Osceola County approves April 1 pay application after contractor reports jail construction 20% complete
Summary
After a contractor update on progress — masonry, HVAC and plumbing largely underway and glazing arriving — the Osceola County board approved an April 1 pay application that itemized roughly $457,000 in construction draws plus separate fees and testing charges.
Get email alerts on the Construction Finance topic
No spam. Unsubscribe anytime.
A contractor updating the Osceola County board on a detention facility said the project is roughly 20% complete and remains on schedule for a September final inspection, and the board approved an April 1 pay application tied to that work.
At the April 14 meeting contractor John reported that exterior masonry is finished, interior metal stud walls and drywall work have begun, HVAC ductwork is complete, plumbing is about 90% done and fire‑sprinkler rough‑in is about 95% complete. "It's probably about 20% complete," John said, adding that detention glazing was due to arrive that week and that September remained the projected month for final inspection.
John presented a detailed pay application and associated invoices. He stated: "You have earned special fees in the amount of $5,100 and reimbursables are $374.56," and later listed construction line items including general construction ($174,696.78), HVAC ($91,999.42), electrical ($83,100.30), plumbing ($31,250.70) and fire‑sprinkler work ($48,664.70). He also noted lab testing, security frames and other charges; the documents as discussed showed a drawn total in the mid‑$457,000 range and a recommended payment application for April 1.
Board members asked clarifying questions about interest and where it appears on the draw schedule; John pointed to an "interest earned" line on the draw schedule and confirmed a recorded interest figure of $5,855.17 that had been added after the initial submission.
After the presentation the board moved to approve the April 1 pay application. A voice vote carried the motion.
The meeting transcript does not show the board approving any changes to the project schedule or scope; members accepted the contractor's schedule update and approved the pay application as presented. The contractor's invoices and the approved pay application will be processed through the county's regular claims and draw schedule procedures.