Committee refers $5,300 change order for Right & 10th Street reconstruction to council

Brainerd City Safety and Public Works Committee · November 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff told the Brainerd City Safety and Public Works Committee that a contractor encountered materials during Right & 10th Street work that required extra handling but tested below disposal thresholds; a roughly $5,300 change order for four and a half crew hours and equipment will be sent to the full council for action.

The Brainerd City Safety and Public Works Committee voted to send a contractor change order for the Right & 10th Street reconstruction to the full City Council rather than approve it at committee. The committee met Nov. 17, 2025.

Mr. Dean, a city staff presenter, said crews encountered potentially contaminated materials while working on the Right & 10th Street project but that testing showed contamination levels were below the threshold that would require off‑site disposal. "We were able to reuse it on site," he said, and the change order request covered additional time and equipment the contractor used to protect, test and handle the material. Staff said the extra work amounted to about 4.5 crew hours and roughly $5,300 in charges.

The recommendation at committee was procedural: staff asked the committee to refer the change order to the City Council for final action rather than approve it at the committee level. Committee members noted a recent, unrelated change order earlier in the year that produced a split committee vote and required a mayoral tie‑breaker at council; that history influenced the choice to move this item to the council for a broader vote.

No formal committee vote to approve the change order was taken; committee members asked questions about the detection date (staff estimated September) and confirmed the work was found consistent with specification 1402 for extra work. The next step is for council staff to place the change order on an upcoming council agenda for consideration.