Committee approves cooperative agreement and observation contract for Highway 210 reconstruction
Summary
Brainerd City’s Safety & Public Works Committee approved a cooperative construction agreement for the Highway 210 reconstruction project, recommended awarding construction observation services (firm name transcribed as "SEW or SH") for $268,000, and discussed responsibilities for as-built drawings.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Brainerd City’s Safety & Public Works Committee on Jan. 20 approved a cooperative construction agreement that lays out construction responsibilities, cost splits and ongoing maintenance for the planned reconstruction of Trunk Highway 210. Staff told the committee the cost estimates included in the draft agreement are preliminary and will be revised once bids are opened and a contractor is selected.
City staff recommended awarding construction observation work for the Highway 210 project to the firm transcribed in the record as "SEW or SH" at a contract amount of $268,000; staff said costs will be split among utility owners and estimated at roughly 85% for water work and 15% for sanitary sewer. The committee approved the recommendation by voice vote; the transcript records only an oral "I" vote and does not list individual votes.
During discussion, a committee member asked who is responsible for preparing and verifying as-built drawings. Mr. Paul (city staff) said it depends on the contract: "Nine times out of 10 city staff or the consulting engineer are going to be doing those as-builts as the construction gets completed," while MnDOT contracts sometimes include a pay item that requires the contractor to prepare as-builts and hire an engineering firm to do so. Paul added that when the city hires professional services, staff expects to be able to rely on the consultant’s data but also reviews work and can verify it internally.
Why it matters: the cooperative agreement and observation contract set roles and cost-sharing for a major corridor reconstruction; clarifying who produces and verifies as-builts affects how the city documents utility locations and accepts completed work.
What’s next: staff will finalize cost estimates after bids are opened and will return contract documents as needed for formal execution.