Wetzel County Schools board approves levy estimates, hears $4.4M in project spending and OKs $2.5M pipeline easement
Summary
The Wetzel County Schools board approved levy estimates for 2026–27, reviewed roughly $4.39 million spent so far on the new school site, and voted to approve a Williams pipeline easement agreement up to $2.5 million to relocate an existing pipeline for the project.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
The Wetzel County Schools board on April 27 voted to approve the district’s 2026–27 levy estimates and moved forward on several items connected to the proposed new school site, including authorizing a pipeline easement agreement with Williams Ohio Valley Midstream LLC.
Board members approved the levy estimates for submission to state agencies after a procedural motion; the board also heard administration updates on site work. Acting superintendent reported geotechnical drilling has begun to inform design and that an archaeological study and student visits are planned. The superintendent said tree-clearing could begin in November without a bat study, allowing grading and earthwork to progress.
Treasurer and administration presented current project-tracking figures for the new school site. The board was given line-item spend details that the administration said total approximately $4,391,683.89 to date. Those costs included land purchases, title and closing fees, multiple phases of due diligence and schematic design work with the engineer Thrasher (most recently a $165,225 schematic-design invoice).
After discussion about contract terms and whether the agreement applies only to the existing pipeline being relocated, the board approved a right-of-way and roadway easement with Williams Ohio Valley Midstream LLC in an amount up to $2,500,000. Board members sought clarification that the easement language covers relocation of the first (existing) pipeline and does not automatically permit unrelated future pipelines without separate agreements. The motion carried following member discussion.
Why it matters: The levy estimates set the framework for the district budget next fiscal year and were considered alongside ongoing, multi-million-dollar site work for a new school. The Williams easement is a necessary step for relocating utilities to clear the build area; the size of the easement payment and the cumulative project expenditures were highlighted as significant budget items requiring continued oversight.
What’s next: The board will return to calendar and budget decisions at its next meeting, and administration said further design and site work will continue pending approvals and schedule coordination with pipeline companies.