Board approves owner contingency and hears construction updates for new Fieldhouse and K2 addition
Summary
District staff requested and the board approved an owner contingency (listed at $220,400) to cover change orders on the Fieldhouse, K2 addition and athletic storage building; staff cited $541,000 in bid-day savings and described unanticipated work such as demolition of existing concrete and a $45,000 finish change for the fieldhouse floor.
Get email alerts on the School Facilities topic
No spam. Unsubscribe anytime.
District staff provided a detailed construction update and asked the board to approve an owner contingency of $220,400 to cover pending change orders tied to the Fieldhouse, the K2 addition and the athletic storage building.
Staff described several categories of change orders: unanticipated demolition (existing concrete footings discovered during excavation), re-engineering foundation work where water was encountered underground, and finish adjustments (the presentation used the example of replacing a specified polished concrete floor with a poly-resin finish to permit athletic use at an estimated $45,000). Staff said these adjustments can be funded from previously approved project dollars and bid-day savings identified by the construction manager, which they reported as approximately $541,000.
The presentation included construction progress photos and a status update: temporary occupancy has been granted for the new baseball/softball concessions and restrooms and boosters have been able to use the concession space for scrimmages. Staff noted some permanent items remain backordered (doors and some exterior finishes) and estimated the upper field turf completion sometime in spring 2026. The boosters have procured a concession trailer and staff are evaluating electrical hookups and placement.
The board approved placing the contingency funds into a purchase order so the district can address remaining change orders through October without adding to the overall project authorization. The approval was recorded by roll call.