Council authorizes bids for Lincoln Avenue alleys and possible parking-lot alternates

Fergus Falls City Council · July 30, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City engineers presented plans and cost estimates for PI5855 (alley paving and storm-sewer work) and three alternates to pave adjacent parking lots; the council authorized the city to advertise for bids, including alternates, and discussed funding mixes.

City Engineer Kyle Meyer presented plans and the engineer’s estimate for PI5855, a reconstruction project covering alleyways between Lincoln Avenue and Cavor and adjacent parking-lot alternates. The base bid (alley/storm work) was estimated at about $280,000; the total alley project cost including contingencies and associated costs was presented at about $385,000. Three parking-lot alternates were estimated at roughly $293,000 combined.

Meyer told council the project responds to utility work that has torn up alleyways; the scope includes pavement replacement and storm-sewer repairs and inlets. Staff outlined potential funding sources: an expected $72,000 contribution from utility companies, roughly $219,500 from a city fund, and approximately $93,500 from Minnesota Streets and Highways (MSA) funding, with an additional portion possibly charged to the stormwater fund depending on final scope.

Council asked whether bidding the alternates raised costs; staff said including alternates in the bid package does not add design cost now and gives flexibility to accept or reject alternates after bids are received. After discussion, a motion to authorize advertisement for bids (including alternates) was made and passed.

Staff will return with bid results and a funding recommendation after bids are opened so the council can choose which alternates (if any) to accept based on actual construction prices and available funds.