St. Peter council approves MPCA‑funded upgrades to Casota lift station
Summary
The council approved a resolution to purchase and install proprietary control equipment, cellular SCADA communications and a backup generator at the Casota lift station, saying the project is supported by an MPCA grant tied to last year’s flooding.
Get email alerts on the Wastewater topic
No spam. Unsubscribe anytime.
St. Peter — The City Council voted Monday to approve purchase and installation of upgraded control and communications equipment at the Casota lift station, a project staff said is largely funded by a Minnesota Pollution Control Agency (MPCA) grant tied to flood‑related work from last year.
Pete, a city public works staff member, told the council the work will replace the existing control panel, add flow monitoring controllers, enable cellular communications to tie the station into the city’s SCADA system, and install a generator to maintain operations during power outages. "This is grant funding from the MPCA, related to flood‑related activities from last year," he said.
The upgrade request was included as a resolution on page 23 of the meeting packet. Mayor Noel thanked Water Resources Superintendent Curtis Thompson for securing the grant and said, "I think residents should feel really good about how often our staff seek grant opportunities for items like this." The council approved the resolution by roll call.
Staff cited a total project cost in the meeting transcript but the numeric lines were garbled in the recording; staff also said the grant would cover the majority of the cost and that the wastewater utility would carry the city’s share. The packet in the council materials is the primary source for exact dollar amounts and budget accounting.
Council members did not request amendments to the resolution at the meeting. City staff said they would proceed with procurement and scheduling under the terms described in the packet and would return with any necessary contract documents or further financial detail.
The council approved the resolution authorizing the purchase, installation and programming of equipment for wastewater improvements at the Casota lift station. The next step is contract execution and scheduling of installation work; staff said they are available to answer follow‑up questions and will coordinate with the wastewater utility on implementation.