Board says science‑wing contractor was terminated; district to advertise bids and may hold special meeting to award
Summary
Board members said a contractor for the science‑wing project was terminated for reasons the district cited as necessary to ensure proper completion; administration will advertise for bids immediately and may hold a special meeting to award a new contract to keep the project on track.
Get email alerts on the Construction Contracts topic
No spam. Unsubscribe anytime.
Board members told the Leonia Board of Education that the district terminated its contractor for the high‑school science‑wing project and is preparing to solicit new bids.
During the meeting the administration said the contractor termination had been included on the consent agenda and that officials "are working as hard as we can" to secure a new contractor and get the project back on track. A board member said, without naming the contractor, that "if you Google the contractor, you'll you'll see why we had to terminate that contract." The board did not publish the contractor’s name in the open meeting.
District officials said they will begin the advertising process for bids immediately and expected to post advertising by the end of the week. If the timing does not align with the board’s regular May meetings, the administration said it might consult with President Lee and schedule a special meeting to award the contract so the project can proceed without undue delay.
Board members urged quick action and flexibility from members: several said they would try to make room in their schedules to meet for a special meeting if necessary. The administration said the planned reopening date for the science wing is still to be determined.
The consent agenda that included the contract termination was approved earlier in the meeting by roll call.