Commissioners discuss courthouse move: 911 phone delays, historic panels and elevator access
Summary
Officials said dispatchers may remain in the old courthouse until a new 911 phone system is installed (likely late June), historic grand-jury panels need careful handling and temporary storage, and elevator access to the secured parking area may require design or retaining-wall work to meet code.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Commission staff updated the commission on details tied to the county's move into a new courthouse, highlighting sequencing and access concerns.
County staff said the vendor-delivered telephone system for 911 has been delayed and that dispatchers may need to remain in the current building until the new system is installed and operational, likely in late June. The county's exchange agreement with the city allows a six-month vacancy window after occupancy; staff said limited short-term access to the current facility will be needed to support dispatch operations.
The county has nine historic grand-jury panels intended for installation in the new building. The panels are long and cannot be maneuvered into the basement; staff said they would be temporarily stored at the EMA building and that road department crews would assist with moving and offloading the panels.
Staff also raised concern that the elevator is not presently secured to the third-floor corridor that leads to the secured parking area. That raises potential code issues because any change that blocks an emergency egress could conflict with fire-code access. Commissioners asked staff and the civil engineer Paxton to evaluate options for meeting code, including potentially addressing the loading-dock and retaining-wall quotes presently under review.
Commissioners said they will coordinate site visits and confirm ramp and dock design before proceeding with final occupancy steps.